dc.description.abstractThe Neelum-Jhelum Hydropower Project, commissioned in April 2018 and located in the Azad Kashmir region of northeast Pakistan, is one of the most challenging and technically complex projects in the region. The project's 28.6 km headrace tunnels are constructed in a highly mountainous region with relatively complex geology that includes various sedimentary rocks of Murree formation. The hydro-mechanical behavior of the deep headrace tunnels with a maximum overburden of 2000 m and underground powerhouse at a depth of 450 m are of particular interest. The project generates electricity by diverting water from the Neelum River to an underground powerhouse through a tunnel system crossing beneath the Jhelum River. The pressurization of the hydraulic tunnels was an important milestone and necessitated intentional planning down to the smallest detail for the first filling. Successful filling was a governing criterion for proper functioning of the tunnel lining that was supplemented by monitoring instruments, a drainage system, and ground treatments during construction of the project. Ground re-saturation during the first filling of the concrete and shotcrete-lined waterways constructed in the diversified rock mass is interesting to study. The rock mass in this area is sheared and fractured, with open fissures. In this study, we investigated the ground re-saturation and water leakages in adits, plugs, and surface outflow after the first filling of the headrace tunnel. A load rejection test was conducted to evaluate overall fitness of the power waterways, plant, and to study any change in leakages due to sudden oscillation in the waterway tunnels. Surfer(3D) software was used to analyze the data collected from the piezometers, which showed abnormal water pressure built up in a localized zone between penstocks three and four. This study was also supported with two-dimensional finite element modeling of the project, at a location where the tunnel has minimum rock cover susceptible to hydrojacking. Numerical analysis results were compared with field data results during the first filling process and both showed close proximity.en_US
dc.description.sponsorshipThe authors (Abdul Muntaqim Naji and Hafeezur Rehman) are extremely thankful to the Higher Education Commission (HEC) of Pakistan for HRDI-UESTPs scholarship. This work was supported by the National Research Foundation of Korea Grant funded by the Korean Government (NRF-2019R1A2C2003636).en_US
dc.language.isoenen_US
dc.publisherSPRINGER WIENen_US
dc.subjectHigh head power planten_US
dc.subjectHeadrace tunnelen_US
dc.subjectConcrete–shotcrete and steel lineden_US
dc.subjectFirst fllingen_US
dc.subjectGround re-saturationen_US
dc.subjectMonitoringen_US
dc.subjectSurfer3Den_US
dc.subjectFinite element modelingen_US
dc.titleGround Saturation Response During First Filling of Lined Pressure Tunnels: A Case Studyen_US
dc.typeArticleen_US
dc.relation.no2-
dc.relation.volume54-
dc.identifier.doi10.1007/s00603-020-02296-9-
dc.relation.page513-535-
dc.relation.journalROCK MECHANICS AND ROCK ENGINEERING-
dc.contributor.googleauthorAhmad, Saeed-
dc.contributor.googleauthorNaji, Abdul Muntaqim-
dc.contributor.googleauthorHussain, Ijaz-
dc.contributor.googleauthorRehman, Hafeezur-
dc.contributor.googleauthorYoo, Hankyu-
dc.relation.code2021001538-
dc.sector.campusE-
dc.sector.daehakCOLLEGE OF ENGINEERING SCIENCES[E]-
dc.sector.departmentDEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING-
dc.identifier.pidhankyu-
Appears in Collections:
COLLEGE OF ENGINEERING SCIENCES[E](공학대학) > CIVIL AND ENVIRONMENTAL ENGINEERING(건설환경공학과) > Articles
Files in This Item:
There are no files associated with this item.
Export
RIS (EndNote)
XLS (Excel)
XML


qrcode

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

BROWSE