Optimal BIM staffing in construction projects using a queueing model

Title
Optimal BIM staffing in construction projects using a queueing model
Author
김재준
Keywords
BIM staffing; Queueing model; BIM RFIs; Waiting time; Waiting cost
Issue Date
2020-05
Publisher
ELSEVIER
Citation
AUTOMATION IN CONSTRUCTION, v. 113, article no. 103123
Abstract
BIM staff plays the important role of providing required information from digital models to project participants. A dilemma is determining the appropriate capacity of BIM staff without sacrificing efficiency in terms of human resource costs. Despite the importance of BIM staffing, its effects on the productivity and performance of construction projects have rarely been investigated. This study presents a framework for quantifying the impact of BIM staffing. First, this study proposes a method to evaluate the activities of BIM staff by introducing a time-dependent queueing model. Second, the proposed framework is validated with data from three real-world projects in which BIM was applied. The effects of BIM staffing on the waiting time of project participants are quantitatively analyzed using time and cost indicators. The results show that decisions about optimal BIM staffing can be made by considering the waiting costs of project participants.
URI
https://www.sciencedirect.com/science/article/pii/S0926580519301761?via%3Dihubhttps://repository.hanyang.ac.kr/handle/20.500.11754/166178
ISSN
0926-5805; 1872-7891
DOI
10.1016/j.autcon.2020.103123
Appears in Collections:
COLLEGE OF ENGINEERING[S](공과대학) > ARCHITECTURAL ENGINEERING(건축공학부) > Articles
Files in This Item:
There are no files associated with this item.
Export
RIS (EndNote)
XLS (Excel)
XML


qrcode

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

BROWSE