300 0

Integrating off-site and on-site panelized construction schedules using fleet dispatching

Title
Integrating off-site and on-site panelized construction schedules using fleet dispatching
Author
한상욱
Keywords
Discrete event simulation; Fleet dispatching; GPS data; Heuristic optimization; Panelized residential construction
Issue Date
2022-05
Publisher
Elsevier B.V.
Citation
Automation in Construction, v. 137, article no. 104201, Page. 1-16
Abstract
In off-site construction, finding good synchronization between the factory and the construction site is critically important. However, in practice, on- and off-site operations are typically scheduled separately, without considering their performance at the project level. For the planning of logistics operations that bridge a factory and sites, this paper proposes a framework to optimize the truck-dispatching schedule using a discrete-event simulation model built based on real fleet operational data (e.g., GPS). Independently pre-planned schedules of factory and site operations are used as inputs, and historical data from transportation equipment are leveraged to generate the dispatching schedule. According to actual panelized residential projects, the proposed framework resulted in approximately 90% of deliveries being made on time, and daily activities were completed on average 40 min earlier than the historical time. Thus, the optimization of on- and off-site schedules may reduce the delays and under-utilization of equipment.
URI
https://www.sciencedirect.com/science/article/pii/S0926580522000747?via%3Dihubhttps://repository.hanyang.ac.kr/handle/20.500.11754/176855
ISSN
0926-5805;1872-7891
DOI
10.1016/j.autcon.2022.104201
Appears in Collections:
COLLEGE OF ENGINEERING[S](공과대학) > CIVIL AND ENVIRONMENTAL ENGINEERING(건설환경공학과) > Articles
Files in This Item:
There are no files associated with this item.
Export
RIS (EndNote)
XLS (Excel)
XML


qrcode

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

BROWSE