BIM-Based 4D Simulation to Improve Module Manufacturing Productivity for Sustainable Building Projects

Title
BIM-Based 4D Simulation to Improve Module Manufacturing Productivity for Sustainable Building Projects
Author
김재준
Keywords
Building information modeling; 4D simulation; sustainability; operation level 4D model; modular construction; schedule management; material quantity management; quality management
Issue Date
2017-03
Publisher
MDPI AG
Citation
SUSTAINABILITY, v. 9, no. 3, Article no. 426
Abstract
Modular construction methods, where products are manufactured beforehand in a factory and then transported to the site for installation, are becoming increasingly popular for construction projects in many countries as this method facilitates the use of the advanced technologies that support sustainability in building projects. This approach requires dual factory-site process management to be carefully coordinated and the factory module manufacturing process must therefore be managed in a detailed and quantitative manner. However, currently, the limited algorithms available to support this process are based on mathematical methodologies that do not consider the complex mix of equipment, factories, personnel, and materials involved. This paper presents three new building information modeling-based 4D simulation frameworks to manage the three elements-process, quantity, and quality-that determine the productivity of factory module manufacturing. These frameworks leverage the advantages of 4D simulation and provide more precise information than existing conventional documents. By utilizing a 4D model that facilitates the visualization of a wide range of data variables, manufacturers can plan the module manufacturing process in detail and fully understand the material, equipment, and workflow needed to accomplish the manufacturing tasks. Managers can also access information about material quantities for each process and use this information for earned value management, warehousing/storage, fabrication, and assembly planning. By having a 4D view that connects 2D drawing models, manufacturing errors and rework can be minimized and problems such as construction delays, quality lapses, and cost overruns vastly reduced.
URI
https://www.mdpi.com/2071-1050/9/3/426https://repository.hanyang.ac.kr/handle/20.500.11754/113236
ISSN
2071-1050
DOI
10.3390/su9030426
Appears in Collections:
COLLEGE OF ENGINEERING[S](공과대학) > ARCHITECTURAL ENGINEERING(건축공학부) > Articles
Files in This Item:
BIM-Based 4D Simulation to Improve Module Manufacturing Productivity for Sustainable Building Projects.pdfDownload
Export
RIS (EndNote)
XLS (Excel)
XML


qrcode

Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

BROWSE